Recent Updates
Floor is Finished!
8/4/2017
The flooring is 70% done, but the rest of the material is delayed from the manufacturer's side. The rest of the floor will be installed probably during the week of the 21st.
Stickwood has been installed on the stage wall
Stage carpet will be started late next week or the week of the 14th.
Starting to Build
7/28/2017
The Visioneering team re-did the floor surface and now it's all flat and leveled.
The floor material arrived, and will be installed mid week next week
2nd layer of paint was done on the walls
Stickwood material for the stage wall arrived, and will be installed next week also.
The demolition is Complete!
7/20/2017
We have removed the flooring and wall fixtures to start the first step of remodeling.
Moisture test was done and the results will be available on 7/24
Bad ceiling tiles are being swapped out
Painting will start on 7/20 and estimated to be completed by 7/26
Starting 7/29 Social Hall will be unusable - activities will resume on 8/27 for the Grand Opening
First Walkthrough for the Construction
7/14/2017
We had our first walkthrough with the design and construction team this week.